First stage of refurbishment in Cerhovice finished

The refurbishment of the factory in Cerhovice, which started in November 2014, has been finished.

In record time of four months, despite the winter season, the whole roofing has been changed, new floors have been laid, power networks have been changed and their input raised to 1.6 MW, new lighting has been installed in the halls, and new ventilation system and sanitary facilities have been finished.

The first two images show part of the building before the refurbishment, the remaining photos show the situation after the refurbishment.